Contract ID: Q465-117M

Estimate Range: Between $3 million and $5 million

Bid Due Date: 02/20/2020 10:30 am

Bids

Alternate Bids (Includes Base Bid Amount)

Engineer's Estimate Base Bid Alt 1 Alt 2 Alt 3 Alt 4
Engineer's Estimate $3,421,029.22
Bidder Base Bid Alt 1 Alt 2 Alt 3 Alt 4
AAH Construction $5,646,620.00