| Project Description | Date Started | Date Completed | | Portions Of Poe Cottage Incl Windows, Doors And Interior & Exterior Finishes. | 8/2/2010 | 9/22/2011 |
| (electrical) Poe Park Visitors Center - Construction Of | 2/19/2008 | 4/11/2011 |
| (h&v) Poe Park Visitors Center - Construction Of | 2/19/2008 | 4/11/2011 |
| (plumbing) Poe Park Visitors Center - Construction Of | 2/19/2008 | 4/11/2011 |
| Poe Park Visitors Center - Construction Of | 2/19/2008 | 4/11/2011 |
| (electrical) Poe Park - Portions Of Bandstand | 3/7/2005 | 6/29/2005 |
| Poe Park - Portions Of Bandstand | 3/7/2005 | 6/29/2005 |
| Play Equipment & Safety Surfaces @ Poe Park (x040) | 11/14/2001 | 11/27/2001 |
| Poe Park | 10/11/2000 | 2/28/2002 |
| Sidewalks & Site Work @ Poe Park (x040) | 12/28/1999 | 7/28/2000 |
| Chain Link Fences, Guiderails, & Steel Fences @ Poe Park (x040) | 9/14/1998 | 2/23/1999 |
| Poe Cottage - Western Red Cedar Hand Split Shake Roof (x040) | 10/16/1997 | 10/31/1997 |
| Fences, Guiderails & General Site Work @ Poe Park (x040) | 10/15/1997 | 11/19/1997 |
| Sidewalks, Paths, Pavements & Sitework @ Poe Park (x040) | 3/10/1997 | 3/25/1997 |