NYC Resources311Office of the Mayor

Rockaway Beach Restoration

Teens enjoy new Rockaway boardwalk with hundreds of beachgoers in the background

After Hurricane Sandy, more than $140 million was invested to repair and restore Rockaway Beach. As part of this work, intact sections of boardwalk were repaired, damaged beach buildings were renovated with new boardwalk islands constructed around them, public restrooms and lifeguard stations were installed to replace destroyed facilities, and interim shoreline protection and anti-erosion measures were created. Thanks to this work, more than 3 million people visited Rockaway Beach last summer.

Even with a successful beach season and better protected peninsula, the recovery of Rockaway Beach is only beginning. We are now working with the Rockaway community, NYC Economic Development Corporation (EDC) and US Army Corps of Engineers on a second phase of improvements – providing more long-term protection for Rockaway, constructing a new boardwalk, and developing a conceptual plan for further improvements to the area’s parks and facilities.

Updates

Work has begun on the Rockaway Boardwalk Reconstruction Project. Read our most recent update for more information.

Sand Ramps

Due to the installation of berms and other service changes, entrances to Rockaway Beach have changed. Visit our Rockaway Beach Access page for more.

 

Community Meetings

Boardwalk Design Presentation for the Rockaway Civic Association

On Thursday, August 14, we presented the Phase 3 preliminary boardwalk design to the Rockaway Civic Association. View a copy of the presentation.

Boardwalk Furniture Design Presentation for the Community Board 14 Parks Committee 

On Monday, August 4, we presented updates on options for boardwalk furniture.View a copy of the presentation.

Boardwalk Design Presentation for the Community Board 14 Parks Committee 

On Wednesday, June 4, EDC presented updates to the boardwalk design since the last community board presentation in January, as well as the latest construction schedule. View a copy of the presentation.

Rockaway Boardwalk Construction Meeting

On Wednesday, March 19, construction logistics and proposed access points for the first (Beach 86th to Beach 97th Street) and second (Beach 97th to Beach 107th) phases of construction were presented. View a copy of the presentation.

Find presentations from past community meetings.

Interim Shoreline Protection and Erosion Control

Geotextile Sandbag Installation

A network of sand-filled geotextile bags has been installed from Beach 55th to Beach 149th Streets. Each section of bags is 100 feet long and composed of interconnected cells that are filled with sand. The bag installation weighs almost 50 million pounds in total, and is helping to provide interim shoreline protection. 

Baffle Walls

More than a mile of replacement baffle walls were installed from Beach 126th to Beach 149th Streets. The baffle walls prevent sand migration and help to protect the adjacent community. The walls are attached to 22-foot steel pilings, driven into the ground, and the concrete portion of each wall extends an average of four feet below grade.

U.S. Army Corps of Engineers Sand Replenishment

Approximately 3.5 million cubic yards of sand are being added to the beach, restoring it to a height and width not seen in decades. The first 600,000 cubic yards have been added from Beach 86th to Beach 149th Streets, with the remaining 2.9 million cubic yards now being placed between Beach 19th and Beach 149th Streets. Some of this sand is being used to cover our geotextile bag installation, forming a stabilized dune. For more information about the Army Corps' project, visit their New York District website.

Rockaway Parks Conceptual Plan

The Rockaway Parks Conceptual Plan is intended as a guide for future improvement of city parks on the Rockaway peninsula from the city limit to Beach 149th Streets, beach to bay, and Broad Channel. The plan will integrate input from community visioning and planning workshops to develop recommendations and priorities for the peninsula.

Find out more about the Rockaway Parks Conceptual Plan.

Environmental Assessment Statement

The reconstruction of the Rockaway Boardwalk required a NEPA environmental review as dictated by the U.S. Department of Housing and Urban Development’s (HUD) Community Development Block Grant – Disaster Recovery (CDBG-DR) program. The final report is posted here.

Was this information helpful?