NYC Resources311Office of the Mayor

Rockaway Beach Restoration

Teens enjoy new Rockaway boardwalk with hundreds of beachgoers in the background

The United States Army Corps of Engineers has resumed pumping sand onto Rockaway Beach in efforts to repair and restore the beach. Access to the beach area from Beach 61st to Beach 19th Streets may be limited while the pumping operation continues. The Corps expects sand placement work to be completed by the end of October, weather permitting. Swimming is not permitted at Rockaway Beach, or any NYC beach, after Labor Day. Please visit the United States Army Corps of Engineers’ website for more information.

After Hurricane Sandy, more than $140 million was invested to repair and restore Rockaway Beach. As part of this work, intact sections of boardwalk were repaired, damaged beach buildings were renovated with new boardwalk islands constructed around them, public restrooms and lifeguard stations were installed to replace destroyed facilities, and interim shoreline protection and anti-erosion measures were created. Thanks to this work, more than 4 million people visited Rockaway Beach last summer.

Even with a successful beach season and better protected peninsula, the recovery of Rockaway Beach is only beginning. We are now working with the Rockaway community, NYC Economic Development Corporation (EDC) and US Army Corps of Engineers on a second phase of improvements – providing more long-term protection for Rockaway, constructing a new boardwalk, and developing a conceptual plan for further improvements to the area’s parks and facilities.

Rockaway Boardwalk

Construction Updates

Work has begun on the Rockaway Boardwalk Reconstruction Project. Read our most recent monthly construction update for more information.

Sand Retaining Wall
Sand retaining wall panels are being installed in the phase 1 area of Roackway Beach from Beach 86th to Beach 97th Street. The panels will be constructed underneath the boardwalk, throughout the boardwalk's entire length. The wall is intented to hold the dunes, as well as the sand beneath the boardwalk, in place. Read our most recent monthly construction update for more information.

sections of sand retaining wall being lowered in place

construction of sand retaining wall

completed sand retaining wall

completed sand retaining wall

Community Meetings

Phase 4B Community Meeting
On Tuesday, October 28, we joined EDC and Skanska in presenting construction logistics for Phase 4B (Beach 60th - Beach 73rd Streets) of the Rockaway Boardwalk reconstruction, as well as the revised access plan for the section, to the Phase 4B community. View a copy of the Phase 4B Construction Logistics presentation and the Phase 4 Access Update presentation

Phase 5 Public Meeting
On Thursday, October 23, we joined EDC in presenting revised access plans to the Phase 5 community. View a copy of the presentation

Rockaway Beach Community Board 14 Parks Committee
On Wednesday, October 1, we presented plans for Phases 3, 4, and 5 and gave a brief introductory overview of Phase 6. View a copy of the presentation.

Find presentations from past community meetings >

Environmental Assessment Statement

The reconstruction of the Rockaway Boardwalk required a NEPA environmental review as dictated by the U.S. Department of Housing and Urban Development’s (HUD) Community Development Block Grant – Disaster Recovery (CDBG-DR) program. View the combined findings/final report

Rockaway Parks Conceptual Plan

The Rockaway Parks Conceptual Plan is intended as a guide for future improvement of city parks on the Rockaway peninsula from the city limit to Beach 149th Streets, beach to bay, and Broad Channel. The plan will integrate input from community visioning and planning workshops to develop recommendations and priorities for the peninsula. Find out more about the Rockaway Parks Conceptual Plan >

Shoreline Protection and Erosion Control Projects

Geotextile Sandbag Installation

A network of sand-filled geotextile bags has been installed from Beach 55th to Beach 149th Streets. Each section of bags is 100 feet long and composed of interconnected cells that are filled with sand. The bag installation weighs almost 50 million pounds in total, and is helping to provide interim shoreline protection. 

Baffle Walls

More than a mile of replacement baffle walls were installed from Beach 126th to Beach 149th Streets. The baffle walls prevent sand migration and help to protect the adjacent community. The walls are attached to 22-foot steel pilings, driven into the ground, and the concrete portion of each wall extends an average of four feet below grade.

United States Army Corps of Engineers Sand Replenishment

The United States Army Corps of Engineers has completed placing 3.7 million cubic yards of sand at Rockaway Beach, restoring it to a height and width not seen in decades. For more information about the Army Corps' project, visit their New York District website.

Was this information helpful?